Main Street Bridge Construction Update – July 22, 2021

by Heather Alvarez | July 22, 2021 11:46 am

Bridge update:

·         There will be no activity July 23-25 due to Mancos Days.

·         The bridge completion is on schedule

·         The north abutment is scheduled to be poured the week of July 26th

Source URL: https://www.mancoscolorado.com/main-street-bridge-construction-update-july-22-2021/